topped out within an hour

This morning, assembly of the steel construction of Building D(emountable) on the cepezed-complex in Delft kicked off. Due to the prefabrication of the steel structure, it topped out within an hour. Part of the steel construction is the elevator shaft shown on the picture. Prefabricated, it was delivered by truck, put in position with a crane and dry-mounted by means of bolts. This kit-of-parts construction method stems from cepezed’s design vision, which takes into account the manufacturability and efficient realization of buildings.

According to plan, the placement of the main load-bearing structure including stairs will be completed within three weeks.  